$500 Million Stadium Lets It Rain with New Waterproofing Technology

Using GCP’s PREPRUFE®, stadium construction was protected with below grade waterproofing
Project
Golden 1 Center
General Contractor
Turner Construction
Applicator
F.D. Thomas
GCP Solution
PREPRUFE® Plus waterproofing
The Overview
The Overview

The Project

Stadium construction on the new 17,500- seat, $507 million Golden 1 Center—the new home of the NBA’s Sacramento Kings—is complicated. The challenge? Time.

The general contractor, Turner Construction, delivered the LEED Gold-targeted arena in less than two years. There’s also the fact that the arena sits below the water table and the immense scale of the task.

"GCP Applied Technologies works with contractors that perform at a very high level and were able to accept the risk due to high performing PREPRUFE® Plus product, technical expertise and global success on similarly critical projects”, said Hunter. “We took the lead in making sure the general contractor, concrete subcontractor, rebar subcontractor and plumbing subcontractor all worked together to meet GCP’s requirements and deliver on the aggressive schedule."

Unfortunately, heavy rains just weeks into the stadium construction project left the excavated jobsite under “… three or four feet of water”, according to Stuart Hunter, Vice President of the waterproofing division of F.D. Thomas, a regional waterproofing contractor. 

The stakes were high. The arena was being built below the water table and adjacent to two major river systems. The owner required a fail-safe below grade waterproofing solution. The Golden 1 Center had to operate dry, period.

Once the skies cleared, the pressure was on F.D. Thomas to waterproof 280,000 square feet (26,012 square metres) within 60 days. No excuses, no delays. F.D. Thomas held pre-job meetings to get all the trades dialed-in to support a smooth, efficient installation.

To meet the requirements for operating dry, the contractors used high performance PREPRUFE® Plus waterproofing membrane. Over 96 rolls of PREPRUFE® Plus membrane (30,000 square feet/2787 square metres) were kicked out in a single day. This allowed F.D. Thomas to finish the stadium construction job in 45 days, shattering all expectations. 

Only PREPRUFE® Plus waterproofing offers a unique combination of industry-leading features for fast, confident application: 

  • Rapidly-deployed kick-out rolls 
  • All-weather seam adhesion with exclusive PREPRUFE® ZIPLAP™ technology 
  • Permanent lateral water migration resistance from an integrally bonded membrane 
  • No-waste, release liner-free installation

The Results

Turner Construction officials were ecstatic with the waterproofing and completion results.  

The owners especially liked the fact that more than 500 million square feet (4,645,152 square metres) of PREPRUFE® membrane have been installed worldwide on thousands of high-profile, must-not-fail projects. As Hunter says, “It’s the industry workhorse”. 

Today the stadium construction project is open to the public and no below grade leaks have been reported in spite of historic El Niño rains and a rising water table. To that, Hunter just grins and says, “Let it rain”.

Blue360sm Total Business Advantage.

The power of GCP products, performance and people.

gcpat.vn | For technical information: asia.enq@gcpat.com


GCP Applied Technologies Inc., 2325 Lakeview Parkway, Alpharetta, GA 30009, USA
GCP Vietnam Company Ltd, Lot B14, Section B, Street No. 12, Xuan Thoi Son Small Scale Arts & Crafts Group, National Road 22Xuan Thoi Son Village, Hoc Mon District, Ho Chi Minh City
This document is only current as of the last updated date stated below and is valid only for use in Vietnam. It is important that you always refer to the currently available information at the URL below to provide the most current product information at the time of use. Additional literature such as Contractor Manuals, Technical Bulletins, Detail Drawings and detailing recommendations and other relevant documents are also available on www.gcpat.vn. Information found on other websites must not be relied upon, as they may not be up-to-date or applicable to the conditions in your location and we do not accept any responsibility for their content. If there are any conflicts or if you need more information, please contact GCP Customer Service.

Last Updated: 2023-09-27

https://gcpat.vn/en-gb/about/project-profiles/500-million-stadium-lets-it-rain-new-waterproofing-technology